Fence Calculator

Enter your fence length and spacing to get a complete material list: posts, rails, pickets and post concrete.

Units
ft
ft
ft

Two rails are common up to 4 ft high, and three for a 6 ft fence.

in

Use the actual width. A nominal 1×6 picket is about 5.5 in.

in
in
in

Go below your local frost line where that applies.

What to buy

  • 14 postsFence posts
  • 39 railsRails, as long as the post spacing
  • 230 picketsPickets, including 5% spare
  • 35 50 lb bagsPost concrete
Fence sections
13 sections
Minimum post length
8 ft
Minimum picket length
6 ft
Concrete around posts
0.48 yd³ (12.9 ft³)
  • Gates, hinges, latches and fasteners are extra. A gate changes the post and picket count.

How the fence materials are calculated

Sections = fence length ÷ post spacing, rounded up
Posts = sections + 1
Rails = sections × rails per section
Pickets = length ÷ (picket width + gap), plus 5%
Concrete per hole = hole volume − post volume

Worked example: a 100 ft straight fence, 6 ft high

This uses 8 ft post spacing, three rails per section and tightly spaced 5.5 in pickets.

  1. Sections: 100 ÷ 8 = 12.5, so 13 sections.
  2. Posts: 13 + 1 = 14.
  3. Rails: 13 × 3 = 39.
  4. Pickets: 1,200 in ÷ 5.5 in = 218.2. With 5% spare, that's 230 pickets.
  5. Each 10 in hole, 24 in deep, holds about 1.09 ft³. A 4×4 post takes up about 0.17 ft³ of that, leaving 0.92 ft³.
  6. For all 14 holes: 12.9 ft³, or 35 of the 50 lb bags at 0.375 ft³ each.

Corners and gates

The formula assumes one straight run. A fence with corners has several runs, each ending at its own post. The simplest method is to enter each run separately, then subtract one post for each shared corner. Gates need their own posts, usually stronger ones, and the opening reduces the number of pickets. Pick the gate hardware first, since it sets the opening size.

How deep should fence posts go?

A common rule of thumb is to bury about one-third of the post's total length, but your local frost line and soil conditions come first. In areas with frost, holes generally need to go below the frost line so the ground doesn't heave the posts. Your local building department can give you the required depth, and may also have rules on fence height and setbacks.

Before you dig